Upgrade works recommence following the holiday break
10 January 2025
Following the Christmas and New Year break, work has recommenced on the Wentworth Falls Lake Precinct upgrades.
Below is a brief update on the current dam wall, spillway, boat ramp and Sinclair Crescent carpark works:
Dam wall: Embankment face upgrade work is complete. Construction work is now underway on the new concrete footpath along the top of the dam wall.
Spillway: Spillway upgrade work will commence next week.
Boat ramp and surrounding area: Construction area fencing is now in place ahead of construction work commencing next week.
Sinclair Crescent carpark upgrade: This is currently in the detailed design phase with construction work anticipated to commence in February/March.