Treeline Lurline project update

17 June 2024

To better match existing street lights widely used across the Blue Mountains, the tops of new light poles on Lurline Street will soon be replaced by the familiar ‘cobra head’ design.

Industrial action by the Electrical Trades Union (ETU) in their ongoing dispute with Endeavour Energy led to a stand-down last week of the crews working on the Treeline Lurline power undergrounding and lighting. This has delayed removal of the two high voltage poles on the corner of Lurline and Waratah Streets and will also delay the replacement of the light poles and installation of five more lights. The work is now planned for early August.