When is this happening?

We commenced night works on 15 November 2020 to implement new street plantings on Macquarie Road.

We will restart works on 11 January 2020 to bring 3 pedestrian crossings on Macquarie Road up to Australian standards and to formalise the parking spaces by marking them out. Works will be undertaken around the clock to shorten the timeframe and minimise disruption.

Stage 1 of the works will commence on the pedestrian crossing at the front of the train station, which will be demolished and constructed.

Once this is complete, Stage 2 will begin with the upgrade of the pedestrian crossing at the front of The Bunker Café. The pedestrian crossing at the front of the Early Childhood Health Centre/IGA will be demolished and constructed at the same time.