Blackheath Village Centre Upgrade

Share on Facebook Share on Twitter Share on Linkedin Email this link

Through the Western Sydney City Deal and the Building Better Regions Fund, we are upgrading Blackheath Village Centre. This is an opportunity to improve the liveability and accessibility of this popular village centre.


Wentworth Street and Govetts Leap Road intersection construction works

11 March 2024

Construction of the Wentworth Street and Govetts Leap Road intersection upgrade works will start on Monday, 18 March 2024.

The intersection improvements include important safety, accessibility and streetscape upgrades, including three raised pedestrian crossings, ramps and sympathetic natural and built landscaping.

Council will continue to liaise with our contractor on the measures to minimise foreseen impacts during construction, however during the intersection works the following is anticipated:

  • Temporary traffic and pedestrian controls will be in place, including fencing for public safety.
  • Current pedestrian ramps will be impacted. However, temporary access ramps will be provided at road crossing points and Pedestrian detours may be required around the work areas..
  • Community facilities located on the ‘Post Office Corner’ will be unavailable.
  • At times, the intersection will be fully closed to vehicle traffic and detours will be in place.
  • Where night works are planned they will generally commence at 6pm and will be completed within a few hours.
  • Some parking spaces around the intersection will be unavailable at varying times during construction.

Council is currently working with the contractor who is delivering the upgrades to finalise a detailed program of works which will guide the construction process. Further detail about this program will be shared once it is confirmed.

We apologise for any inconvenience or disturbance while these improvements are constructed.


Underground services location survey

7 March 2023

On the evening of Thursday 7 March 2024, an underground services survey will be occurring around the intersection of Wentworth Street and Govetts Leap Road in Blackheath Village Centre.

There will be no noise or disruption to surrounding residents.

The survey is being conducted at this time to ensure there will not be any impact to business or the community, but residents may notice some markings on the street and pavement following the survey work. Some minor traffic controls will be in place while the survey is conducted.



This project is funded under the Western Parkland City Liveability Program which is part of the Western Sydney City Deal, and the Building Better Regions Fund.

The Western Sydney City Deal is a partnership between the three levels of government overseen by the Minister for Infrastructure, Transport, Regional Development and Local Government, the Hon. Catherine King MP, the NSW Minister for Enterprise, Investment and Trade, the Hon. Alister Henskens SC MP, and the eight Mayors of the Western Parkland City.


Through the Western Sydney City Deal and the Building Better Regions Fund, we are upgrading Blackheath Village Centre. This is an opportunity to improve the liveability and accessibility of this popular village centre.


Wentworth Street and Govetts Leap Road intersection construction works

11 March 2024

Construction of the Wentworth Street and Govetts Leap Road intersection upgrade works will start on Monday, 18 March 2024.

The intersection improvements include important safety, accessibility and streetscape upgrades, including three raised pedestrian crossings, ramps and sympathetic natural and built landscaping.

Council will continue to liaise with our contractor on the measures to minimise foreseen impacts during construction, however during the intersection works the following is anticipated:

  • Temporary traffic and pedestrian controls will be in place, including fencing for public safety.
  • Current pedestrian ramps will be impacted. However, temporary access ramps will be provided at road crossing points and Pedestrian detours may be required around the work areas..
  • Community facilities located on the ‘Post Office Corner’ will be unavailable.
  • At times, the intersection will be fully closed to vehicle traffic and detours will be in place.
  • Where night works are planned they will generally commence at 6pm and will be completed within a few hours.
  • Some parking spaces around the intersection will be unavailable at varying times during construction.

Council is currently working with the contractor who is delivering the upgrades to finalise a detailed program of works which will guide the construction process. Further detail about this program will be shared once it is confirmed.

We apologise for any inconvenience or disturbance while these improvements are constructed.


Underground services location survey

7 March 2023

On the evening of Thursday 7 March 2024, an underground services survey will be occurring around the intersection of Wentworth Street and Govetts Leap Road in Blackheath Village Centre.

There will be no noise or disruption to surrounding residents.

The survey is being conducted at this time to ensure there will not be any impact to business or the community, but residents may notice some markings on the street and pavement following the survey work. Some minor traffic controls will be in place while the survey is conducted.



This project is funded under the Western Parkland City Liveability Program which is part of the Western Sydney City Deal, and the Building Better Regions Fund.

The Western Sydney City Deal is a partnership between the three levels of government overseen by the Minister for Infrastructure, Transport, Regional Development and Local Government, the Hon. Catherine King MP, the NSW Minister for Enterprise, Investment and Trade, the Hon. Alister Henskens SC MP, and the eight Mayors of the Western Parkland City.


  • Start of the upgrade work

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    October 2023

    Construction of the liveability, safety and accessibility upgrades in Blackheath Village Centre has commenced and is expected to be completed in December 2023.

    What work will be taking place?

    The work is being delivered in several stages at different locations within the village centre. Please find below a summary of the upcoming construction works:

    1. Upgrades to the facilities and landscaping of the Great Western Highway road reserve. This is the area adjacent to Neate Park that runs along the highway to the Rotary Clock Corner (the southwest corner of the Great Western Highway and Bundarra Street intersection).
    2. Renewal of the Sutton Lane Car Park (South side of Sutton Lane).
    3. A new pedestrian crossing at the intersection of Sutton Lane and Wentworth Street.
    4. Formalisation of on-street parking along Station Street, between the station commuter carpark and the intersection of Bundarra Street and Station Street.
    5. Footpath renewal and on-street parking upgrade on Gardiner Crescent at the frontage of the Blackheath Community Neighbourhood Centre.
    6. Renewal of the footpath along Wentworth Street.

    View a map showing the numbered work sites.

    Construction works will take place between 7am – 6pm Monday to Friday and 8am – 1pm on Saturdays.

    Construction traffic will be managed by Council’s contractors who have been engaged for the upgrade works. Some noise and vibration will occur from the construction works. However, active efforts will be made to eliminate and mitigate noise and vibration where possible.

    Please note that the planned works for the Wentworth Street and G

  • Update on Sutton Lane Carpark construction timeframe

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    19 December 2023

    Unfortunately, the reopening of Sutton Lane carpark has been delayed. The carpark will now reopen to the public on Saturday, 23 December 2023.

    The short delay is the result of design improvements being identified and delivered as part of the upgrade work.

    We appreciate the community’s patience and apologies for any inconvenience.

  • Station Street upgrades

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    7 December 2023

    Upgrade work along Station Street, between Railway Avenue and Bundarra Street, is scheduled to commence on Monday, 11 December 2023 with an estimated completion date of Friday, 22 December 2023.

    There will be a partial road closure and detour in place for traffic heading South towards Bundarra Street on Station Street. Traffic Control will be in place to assist in the movement of vehicles.

    We apologise for any inconvenience caused and appreciate your co-operation during this time.

  • Update on Sutton Lane Carpark construction timeframe

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    7 December 2023

    Due to recent wet weather, completion of the Sutton Lane carpark upgrades has unfortunately been delayed.

    The carpark will now be open on Saturday, 16 December.

    The upgrade work includes:

    • Resurfacing and repairing the carpark.
    • Reconfiguring the carpark to provide more parking spaces.
    • New line marking which will also clearly identify accessible parking bays and the turnaround bay.
    • Installing improved signage.

    We greatly appreciate the community’s patience as this work is completed. Please be assured we are working with our contractor to ensure the work is finished as soon as possible.

  • Sutton Lane Carpark upgrade

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Sutton Lane Car Park upgrades - 13 November to 8 December 2023.

    As part of the Blackheath Village Centre Upgrade Project, Sutton Lane Carpark will be closed from Monday, 13 November 2023 to Friday, 8 December 2023.

    During this time, there will be no access to the carpark.

    This necessary upgrade work is being prioritised to ensure it is completed as quickly as possible.

    The upgrade work includes:

    • Resurfacing and repairing the carpark.
    • Reconfiguring the carpark to provide more parking spaces.
    • New line marking which will also clearly identify accessible parking bays and the turnaround bay.
    • Installing improved signage.

    We greatly appreciate the community’s patience as this work is completed. Please be assured we are working with our contractor to ensure the work is finished as soon as possible.

  • Blackheath Village Centre upgrade design update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    August 2023

    Updated designs for the village centre upgrade works are now available from the Document Library.

  • Blackheath Rail Building – Public Art EOI

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Blackheath Rail Building – Public Art EOI has now closed. Thank you to everyone who submitted an EOI.

    Council called for Expressions of Interest (EOI) from sculptors and artists to develop a site-specific public artwork as part of the planned improvements to Blackheath Village Centre. This project is one part of a broader village upgrade project and is funded by the Build Better Regions Fund (BBRF), the Western Parkland City Liveability Program Fund (WPCLP) and Council’s contribution.

    This project will deliver a new, site-specific sculptural artwork within the area around the Blackheath Rotary Clock and Neate Park. The purpose of the artwork is to visually screen the dilapidated rail building and add aesthetic interest to the Village Centre and arrival experience to Blackheath. The sculpture is to be a well-made work that is suitable for an outdoor public environment.

    Council is looking for an artist to design the site-specific artwork consistent with one or more of the following key principles:

    • Sensitivity to the aesthetic qualities of Blackheath Village
    • Contextual responsiveness to Ngurra (Country)
    • Potential to portray local and town stories
    • Collaboration with local community members in the creation of the work
  • Wentworth Street and Govetts Leap Road intersection (works package 3) update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    June/July 2023

    The Blackheath Village Centre upgrade has progressed into a detailed design phase, including improvements to the Wentworth Street and Govetts Leap Road intersection. This option was the approved design to meet traffic engineering, pedestrian compliance and accessible outcomes. To see the design, view the information flyer.

    The detailed design for the other work packages continues and more information will be shared with the community when available.

    For an overview of the six work packages, please see the news feed below or view the documentation available on the right.

  • Project Update - April 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Project Update

    April 2023

    A project update presentation is now available, including:

    • A project overview
    • Progress update on the various work packages
    • Consultation outcomes and design commentary

    View or download the presentation.

  • Update: 6 April 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Update 6 April 2023

    Following community consultation on the upgrade in late 2022 and early 2023, the Blackheath Village Centre upgrade plans have progressed into a more detailed design phase. Consultation comments were reviewed and considered for the detailed design where practically suitable supported by Traffic Engineering and Heritage and Environment teams.

    Below is a brief update on the progress of each package that makes up this important upgrade project:

    Package 1 – Sutton Lane Carpark, Sutton Lane Crossing & Station St Carpark

    • Preliminary design and internal review completed.
    • Proposed layouts submitted for next stage approval such as the Local Traffic Committee for consideration at the mid-April meeting.
    • Proposed layouts will be provided to external stakeholders such as the Access Advisory Committee in the coming weeks
    • 50% detailed design is in progress.

    Package 2 – Footpath Renewal and Hall frontage accessible parking

    • Assessment of the existing footpath and ramps completed.
    • Footpath renewal details are under review, including an arboricultural impact assessment to ensure tree viability.
    • Proposed layouts will be provided to external stakeholders such as the Access Advisory Committee and BANC in the coming weeks
    • Detailed construction design is in progress.

    Package 3 – Govetts Leap Rd and Wentworth St crossings and the former Post Office corner Streetscape

    • Layout option studies and analysis completed with various internal teams, supported by our engaged design consultancies.
    • Preliminary set-out plan completed.
    • 50% detailed design and cost plan is in progress.
    • Proposed layouts submitted for next stage approval such as the Local Traffic Committee for consideration at the mid-April meeting.
    • Proposed layouts will be provided to external stakeholders such as the Access Advisory Committee in the coming weeks

    Package 4 – Neate Park and Rotary Clock Area Enhancements

    • Options for the main elements of this component of the upgrade were explored and analysed, with input from internal experts and external consultants.
    • Detailed surveys including location of underground services such as Sydney Water and NBN completed and design impacts/restrictions steering designs.
    • Draft 50% detailed design completed for review.
    • Expressions of Interest for the design of the screening feature in front of the railway building will be sought soon.

    Package 5 – Govetts Leap Statue conservation

    • Structural assessment of the Statue and condition assessment of the Statue exterior coating completed.
    • The original construction method and material were investigated, and an initial cleaning and repair method is proposed as a starting point for engaging suitable artists/craftsmen.

    Package 6 – Visitor signage and Heritage Trail

    • The graphic design work for the detailed trail plaques is well progressed, along with draft specifications for manufacture and installation.
    • A licensed website to host the trail map and interpretation content of the seven historical sites has been obtained.
    • Draft historical background and interpretation content of the sites was completed and is under review.

    The construction works are anticipated to roll out from late August to December 2023.